Triggering job to start after another job completes


Forum|alt.badge.img

We have 2 jobs

Job 1 runs at 11pm and normally runs 1 hour. 

Job 2 runs at 1am and must run after Job 1 completes, this job usually runs for 6 hours. 

On occasions Job 1 runs 3 hours and this causes job 2 to miss it start window.

 

How can I adjust the schedule so that Job 2 has 2 criteria?

   1-Job 1 completes

   2-Has to start after 1am

Best answer by Christian Hauggaard

Hi @rholmes this is currently not possible. Please submit an idea in the ideas section. A future potential workaround to this could be using the API for “triggering and monitoring task executions”, however at the moment this is still in closed beta testing.

View original
Did this topic help you find an answer to your question?

2 replies

Christian Hauggaard
Community Manager
Forum|alt.badge.img+5

Hi @rholmes this is currently not possible. Please submit an idea in the ideas section. A future potential workaround to this could be using the API for “triggering and monitoring task executions”, however at the moment this is still in closed beta testing.


AvanWijnen
Employee
Forum|alt.badge.img
  • Employee
  • 23 replies
  • April 21, 2023

Hi @rholmes,

Which version of TimeXtender are you running? 

Where do you run the jobs (e.g. ODX, MDW or SSL)?

//Alex